Sidewalks needed on both sides of 132nd between Sunnyside and Hubbard
-
Sidewalks needed on both sides of 132nd between Sunnyside and Hubbard
-
Sidewalk here is only one side - percentage seems high
-
Should be continuous sidewalk from 224/Webster to south to Roots Rd
-
Johnson Creek Rd and I-205 and Johnson Creek Rd and Fuller intersections - limits ability and access
-
Fuller Rd/ King and King/80th disconnect
-
Carver Rd overpass - what happens to system if not constructed?
-
Monterey gap from Stevens to Schumaher
-
U123 - sidewalks really needed on 129th
-
Clackamas River Dr landslides - not likely to be widened
-
Fix lights - get L-turn on Webster Rd
-
Congestion is building - light coordination could be stronger; left turn stop sign and exit to S 205 has created some accidents
-
Carver boat ramp on weekends - very congested during the summer weekends
-
Very important to complete Mather Rd. bikeway between 97 and Summers Ln
-
Show HU ped "path" system and public property of worship - would allow you to assess alternatives other than street grid
-
I-205 bike path disconnect
-
Oetkin Way & Naef Rd = bike blvd
-
Shuttles to Park Ave Station for large retirement communities along River Rd.
-
Sidewalk gap - Johnson city to Webster, nothing on North side
-
Delete ALL neighborhood interior street walks
-
Delete interior walks - Molt St, Aldercrest, etc
-
Delete interior neighborhood walks
-
Delete interior neighborhood walks
-
Frequent crosswalks (e.g. 600 ft)
-
Harmony Rd. connect to Toys R Us bu avoid three creeks